The Project Charter – Constraints

Initiation

Constraints are any limitations to solution options that have been imposed on a project. It is important to know these early on so time is not wasted pursuing these options. Here are some examples:

  • The solution must work with Microsoft Edge as that is the company standard
  • The solution must be an Oracle product for seamless integration with our other Enterprise systems
  • The new department we are adding as a result of this project must fit into this 30′ x 50′ area

When project constraints are uncovered, be sure to understand the reason why. It is possible some constraints could be removed. I was involved with a project where the service provider was already selected but without looking at the competition. I convinced my business partners to conduct formal “Request for Proposal’s” with the leading competition and the result was a different provider was selected.

Constraints are included in the Project Charter so that the Sponsor and Core Project Team understand and agree.

My Kindle Book, “Project Management For The Real World”, is available at

http://www.amazon.com/do/b089krddvn

Now available in paperback!

Advertisement

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s