The Project Charter – Timeline

Initiation

The Project Charter should contain a high-level timeline so that expectations can be set and preliminary commitments established. If not enough is known at Charter time to be reasonably certain of this timeline, then it should be noted as to when the baseline schedule will be established.

The timeline will contain elements that depend on your organization’s methodology. You will want to note target completion dates for major milestones and phases. Here is an example for a software development project:

  • Requirements – Jan 31
  • Design – Feb 23
  • Development/Unit Testing – April 8
  • System Testing – April 30
  • User Acceptance Testing – May 21
  • Transition to Production – June 8
  • Production Stabilization – July 8

For projects not involving software, your phases and major milestones will be named according to the nature of the project. Here is an example where the project is to order and install new equipment in several locations:

  • Scope established – Jan 15
  • Products Ordered – Jan 30
  • Products Tested – Feb 21
  • Products installed in pilot locations – March 15
  • Products installed in all locations – June 1
Advertisement

The Project Charter – Scope of Work

Initiation

At the Project Charter level, the scope of work is not meant to be all-inclusive and at a fine level of detail. That is done when detail requirements are addressed.

You can derive part of the scope by taking each Project Objective (refer to the post on Project Objectives for more detail) and listing the major work activities needed to accomplish that objective. These should be at a level of detail enough to get a high-level understanding of the effort and duration of the activity. This is a judgment call and varies by type of project.

In addition to the above, you can list the major business processes that are impacted by the project. A process is impacted if one of the following is true:

  • there will be new or changed process steps
  • there will be new sources of data or information for the process
  • there will be new recipients of data or information from the process
  • there will be changed or additional owners of the process.

Listing the major activities and the impacted processes should be sufficient for scope at the Project Charter level. Your organization’s standards may require more, but this should be the minimum.

The Project Charter – Project Objectives

Initiation

In the previous post I defined and discussed Business Objectives and their importance. Project Objectives are very different from Business Objectives. I have seen Project Charters with the two types of objectives mixed into one objectives section and I find it very confusing. I recommend placing Project Objectives in its own section.

Project Objectives should satisfy the following criteria:

  • Produce a product, service or result that survive and are maintained after the project is over. Some examples of this are (1) a new business “Standard Operating Procedure”; (2) new software installed that meets all of the acceptance criteria.
  • Each Objectives should have a definition of “done” that is agreed to by the Project Sponsor and the Project Team.

Project Objectives are important for the following reasons:

  • They define the scope of the major deliverables of the project
  • They will be used to define much of the activity scope of the project
  • Meeting all of the Project Objectives is one of the criteria for project closing

The combination of having well defined Business and Project Objectives will get your project off to a great start and help keep it on track. Take care to get these right.