The Project Health Scorecard Part 3 – Scope Health

Executing Monitoring and Controlling

Here is the suggested guidance for the status of the Project Scope Health:

Your Scope Health is Green if all of these are true:

  • You have an approved Project Charter
  • Scope is defined in the Charter
  • There is a defined scope change request process

Your Scope Health is Yellow if all of these are true:

  • You have an approved Project Charter
  • Scope is defined but there are significant change requests pending Executive Sponsor review and approval

Your Scope Health is Red if one of these is true:

  • Scope is not defined
  • Scope is defined and there is no approved scope change process
  • The defined Scope change process is not being followed.

Note: Much more detail on the Project Health Scorecard can be found in my Kindle book “Project Management For The Real World”, available at

https://www.amazon.com/author/lettera

Advertisement

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s