Building Blocks of a Successful Project Part 4 – Human Resources

Initiation

The first step in obtaining your project’s human resource needs is to create a “Roles/Responsibilities” matrix. In the first column, you define the project roles required. For example “Project Manager”, “Business Analyst”, “Subject Matter Experts”. These are not job titles but roles defined for the needs of the project. The second column describes the scope of responsibilities for that role. The third column is the name or names of those people assigned to that role. The rest of the columns contain contact information, and the assignee’s department and manager.

The next step is obtaining the commitments for these resources to work on the project. I have seen many projects given the approval to begin without the commitment (or even awareness) of key stakeholders (business units that will have project task assignments). This leaves the Project Manager in the position of negotiating with the business units for resource time and priority. This is typically the result of lack of Project Portfolio Management and control of the project intake process, especially in regard to resource capacity.

A best practice in Project Management is to secure the resource commitments prior to the approval of the Business Case. This means doing a thorough stakeholder analysis of all of the roles and responsibilities needed for the project. A brainstorming session with those having a broad knowledge of the business functions can help identify key stakeholders.

The Executive Sponsor (with support from the Project Manager) is responsible for communicating with the affected business units and securing the commitments. If these commitments have not been made and the project is directed to proceed, then this must be handled using formal Risk Management (which will be addressed in a future post).

In addition to having committed resources, they must also be the right resources. They must have skills that match the assigned roles. If they don’t and you have no resource alternatives then your project must include a plan for skills development and your task estimates must take into account the skill levels of the task assignee.

For your “core” team (the small group that attends almost all meetings and contribute to planning) you must make sure they are empowered as decision makers. If your team is constantly saying “I have to get my manager’s approval”, your schedule may be significantly impacted.

Advertisement

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s