The Project Health Scorecard Part 1: Schedule Health

Executing Monitoring and Controlling

Here is the suggested guidance for the status of the Project Schedule Health:

Your Schedule Health is Green if:

            • You have a schedule
            • It is actively managed
            • The forecast matches the published completion date

Your Schedule Health is Yellow if:

  • It is early in the project and you don’t have a schedule but are working towards one, or…
  • You have a schedule and the forecast has a greater “live date” than the current published date but corrective action is defined and probable
  • The schedule is not being actively managed.

Your Schedule Health is Red if:

  • You don’t have a schedule, or…
  • You have one but the published live date cannot be met.
  • Red can turn back to Green when a new schedule is approved and base-lined.